kt
/ENG        
 

工程回顧

以下是我們自2001年成立以來曾參於的重要工程項目

  • 2001-2005s
  • 2006s-2009s
  • 2010s-2014s
  • 2015s-現在

2001

    - Dismantling and Installation Oil Transformer and RMU
    - Installation T.X. CT Frame and T.X. Cable Frame
    - 400/132kV 240 MVA Oil Transformer Replacement Work

2002

    - 400kV GIS Extension(GIS portion)

2003

    - 400kV GIS Extension(GIS portion)
    - Vaccum Chamber Installation for Oil Regeneration Plant
    - Installation 1000 MVA Series Reactor
    - Installation and remove the Pump station

2004

    - C7 & C8 Installation
    - Miscellaneous Items for 11kV DBB GIS Erection
    - Replacement of New Model Dephydrating Breather
    - U7 & U8 Electrical Equipment Installation (Electrical work)

2005

    - U7 & U8 Electrical Equipment Installation (Electrical work)
    - C8 MV Installation
    - Installation 1000 MVA 275kV Shunt Reactor
    - Installation of 132/11kV Gas Transformers
    - Installation Laying and Termination of Multi-core Control Cables
    - Remove of 50 MVA 132/11kV Transformer No.1
    - 400kV GLS Extension (Mitsubishi H1S5449)
    - Checking and repairing U7 and U8 Generator Transformer, Dismantling and Assisting Testing U8 Generator Transformer and Installation of drain vessel piping system for U7 and U8b HRSG

2006

    - 400kV GIS Extension(Mitsubishi H1S5447 and H2Y1409)
    - Remove of 80MVA 132/33kV Transformer
    - 87 MVAR 145Capacitor Bank Installation Work
    - Erection 13 x 11kV VATeach Switchgear
    - Remove of 80MVA 132/11.8kV Transformer CG5/CG6

2007

    - 400kV GIS Extension(Mitsubishi H1S5447 and H2Y1409)
    - Relocation of A1 Unit Transformer
    - Supply & Installation the Ventilation Fan System
    - Replacement of 1 x 132/11kV Transformer
    - Panel Installation, Panel Testing and HV AC Testing for new 11kV Siemens GIS
    - Erection of Norte Substation- Stage 2(Macau)
    - Erection of Norte Substation- Stage 3(Macau)
    - Erection of 110/66kV Norte Substation - Stage 1
    - Erection of 66/11kV Switching station for city of dreams

2008

    - Panel Installation, Panel Testing and HV AC Testing for New 11kV Siemens GIS
    - 400kV GIS Extension(Mitsubishi H1S5447 and H2Y1409)
    - General Transformer Replacement of LV Turrent Gasket and Bellows
    - Remove and Installation for Radiator
    - Installation of 275kV Shunt Reactor & Associated Equipment
    - EC project SCR Installation work
    - Erection of 110/66kV Norte Substation - Stage 1
    - Erection of city of dreams 66/11kV S/S
    - Erection of 110/66kV Norte Substation - stage 2
    - Erection 66/11kV 50 MVA Power Transformer at Venetian Parcel 5 & 6 66kV Substation

2009

    - Installation of 275kV Shunt Reactor & Associated Equipment
    - EC project SCR Installation Works
    - General Transformer Replacement of LV Turret Gasket and Bellows
    - Installation of 11kV Cables and Cable Tray System for FGD Loads
    - Replacement Work of 35 MVA Gas Insulated Transformer
    - Erection of 110/66kV Norte Substation - stage 2
    - Erection 66/11kV 50 MVA Power Transformer at Venetian Parcel 5 & 6 66kV Substation
    - Erection Transformer, Cables Laying and Terminations for Norte 110/66kV Transformer T3


2010

    - Installation of 11kV Cables and Cable Tray System for FGD Loads
    - Replacement Work of 35MVA Gas Insulated Transformer
    - CEM Substation Extension for City of Dreams

2011

    - Black Point Gas Supply Project Construstion Works (M2554/SC/020)

2012

    - Black Point Gas Supply Project Construstion Works (M2554/SC/020)
    - Gas Heater Emission Test
    - Installation and Testing Assistance of 400MVA 275/16kV Unit 9 Generator Transformers
    - Installation and Testing Assistance of Standby Unit 9, GT57 and Common Transformers
    - Replacement of Existing Transformers and Installation of New 132/6.6kV Transformer No.1 & No.2 with Associated Equipment
    - Installation 6.6kV Switchgear Unit C3
    - Replacement of the Corroded Air Duct of #3 Heater in GRS Hong Kong

2013

    - Black Point Gas Supply Project Construstion Works (M2554/SC/020)
    - Sub-Contract No.H2514-ME - 3536 Supply of Pipe Fitters for Piping Work for Plant A & B

2014

    - GRS Inlet & Outlet Filter Replacement
    -Overhauling the Blower motor of GRS Sale Gas Heater #6
    - Replacement of #6 Heater Tank

2015

    - Replacement of #6 Heater Tank
    - Overhauling the Blower Motor of GRS Sale Gas Heater#1
    - CR for GRS 2015 Metering Tube Cleaning
    - Hitachi 132kV GIS Refurbisment
    - Transformer Oil Replacement in GBG

2016

    - Hitachi 132kV GIS Refurbisment
    - 龍鼓灘末站運行維護服務
    - Generator Transformer Bushing Replacement

2017

    - Hitachi 132kV GIS Refurbisment
    - 龍鼓灘末站運行維護服務
    - Generator Transformer Bushing Replacement
    - 龍鼓灘末站運何維修服務西氣東輸香港支線管道清管作業

2018

    - 龍鼓灘末站運行維護服務
    - Generator Transformer Bushing Replacement
    - 2018年香港終端日常維修服務